Riyadh Metro Package A
2026-07-02 · day shift · clear
Progress
42%
Manpower
126
Equipment
18
Summary: Concrete pour completed for Zone B; MEP rough-in started on Level 2.
Blockers: Permit coordination and material delivery window need follow-up.
Safety: Toolbox talk completed; heat stress controls active.