Progress, manpower, blockers, safety notes

Daily field reports

Premium construction safety operations for board-level visibility: site risk, field evidence, corrective actions, and audit readiness.

Riyadh Metro Package A

2026-07-02 · day shift · clear

submitted
Progress
42%
Manpower
126
Equipment
18

Summary: Concrete pour completed for Zone B; MEP rough-in started on Level 2.

Blockers: Permit coordination and material delivery window need follow-up.

Safety: Toolbox talk completed; heat stress controls active.